Sunday, December 13, 2009

Sub Flooring

This week we began putting in the sub flooring on the second story (12/7 - 12/11).

Monday: We put up the floor joists that our sub flooring will be laid on top of.

Tuesday: Started installing the 3/4 inch plywood as the sub flooring. Started pre-cutting pieces for a small 2 foot high wall that would run the width of the house over the garage.

Wednesday: Some of us built the small wall and had it lifted up and put in place, while the others kept adding plywood for the sub floor.

Friday: We installed our bottom and top plates around the perimeter of the sub flooring so we could begin marking our studs, headers, and interior walls.


No comments:

Post a Comment