Monday, November 9, 2009

Stemwall Pour

Week (11/2 -11/6)


Monday: Today we put up scaffolding and added a railing for safety, cut re-bar that would later be placed in the stemwall for support, and made other preparations for pouring the stemwall.


Tuesday: Continued to cut the re-bar, put up some more turnbuckles to help keep the walls in place, put the last of the ARRX blocks on.


Wednesday: We made the Final preparations for the pour, we tied the re-bar inside the wall, tied the blocks down secure, and poured concrete today. Some of our crew stayed later to help finish the pour while the rest left.


Friday: cleanup, made sure our site was all nice and tidy so we could move on to the next step.